Approving AI Data Centres in the NT – no easy feat
17 November 2026
The NT is primed to become a key player in Australia’s emerging data centre industry as land, water and power become essential, expensive commodities. However, recent delays to Energy North’s ‘hyperscale’ AI data centre Project Ares reveal the regulatory challenges that could impede Australia’s progress in the burgeoning industry.
The proposed 1GW AI data centre located on Murranji Station in the Barkly Region, approximately 683km south of Darwin was expected to commence operations in June 2028, but Energy North has been held up by the Northern Territory Environmental Protection Authority’s (EPA) assessment of the project.
The AI boom has been at the forefront of many developers’ minds in the past months, with states and territories and the federal government racing to meet demand head-on. As the planning regime struggles to keep up with an industry it was not designed for, developers such as Energy North have experienced first-hand the teething problems in the developing policy regime.
In this article, we explore the planning regulations that apply to data centres in the NT, and how those may change as national policy develops.
Environmental approvals
Energy North initially referred Project Ares to the EPA for its ‘significant environmental and social impacts due to its large scale and the extent of disturbance proposed’ (Energy North’s Referral Form, publicly available on the EPA website).
On 15 September 2026, the EPA made the decision to require an environmental impact statement (EIS) to assess Project Ares, citing the potential for a significant impact on 10 environmental factors. The EPA also identified that federal AI policy was under development and this would inform the requirements of the EIS assessment. The EIS terms of reference are currently being finalised. The EPA suspended its statutory timeframe to enable consultation with the National Environmental Protection Agency (NEPA).
Energy North also referred the project to NEPA under the federal Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act). NEPA’s further assessment is also ongoing, after confirming that the project was a controlled action as it could impact threatened and migratory species.
Land use approvals and community consultation
If Project Ares secures the required environmental approvals, Energy North will need to contend with further planning and land use requirements. Under the NT planning scheme, Energy North must apply directly to the Minister for Lands, Planning and Environment for planning approval.
Unlike other jurisdictions the NT does not currently have any community licence or engagement guidelines or framework specific to data centres. This means that proponents of data centres in the NT can seek approval from the consent authority without meeting any community engagement requirements specific to data centres.
However, developers must cooperate and negotiate with Traditional Owners.
Around half of the land in the NT is Aboriginal land under the Aboriginal Land Rights (Northern Territory) Act 1976 (ALRA) which grants legal protection to Traditional Owners. Section 70 of the ALRA makes it an offence for a person to enter or remain on Aboriginal land without a permit or interest in the land. Developers may need to negotiate a lease or other interest under s 19 of the ALRA to undertake their activities on Aboriginal land. The NT’s extensive legislation protecting cultural heritage such as the Northern Territory Aboriginal Sacred Sites Act 1989 may also be relevant.
The land rights of Traditional Owners are also protected through the Native Title Act 1993. Energy North has indicated that it will need to negotiate an Indigenous Land Use Agreement (ILUA) with the Northern Land Council on behalf of the native title holders of the Newcastle Waters-Murranji area (DCD2007/002) under the Native Title Act 1993 to access the land subject of its proposed data centre.
Federal policy on AI development
The NT government is supportive of data centre development as well as their reliance on natural gas.
However, the Australian Standards for AI, which were announced by the Australian Government in July 2026, would require data centres to build new renewable energy generation capabilities and be ‘net-generators’ of power. The legislation is expected to be passed in early 2027.
Energy North claims that Project Ares will have no grid dependency and generate up to 3,000 MWp of solar power. However, the project will also rely on up to 1,038MW of gas generation which could pose a challenge in light of the Federal Government’s proposed standards.
For more information on the federal government’s AI Standards, you can read Jason Kwan’s article on the subject here.
The Federal Government has also indicated that it intends to work with state and territory governments to develop community engagement frameworks which could see the NT introduce guidelines for community consultation which mirror the strategies already implemented in other states.
In addition to the shifting sands of national and state policy regarding data centres, the scale of AI data centres means that a variety of federal entities may need to be consulted in the assessment process. For example, fibre optic and submarine cables are regulated through the Telecommunications Act 1997 and energy reporting requirements may be relevant under the National Greenhouse and Energy Reporting Act 2007.
What does this all mean for developers?
The extensive approval process required for data centre development, as well as the evolving regulatory landscape mean that serious delays could be experienced for new projects.
However, the Project Ares data centre was awarded ‘Major Project Status’ by the Major Projects Facilitation Agency, a Commonwealth initiative which grants strategically significant projects which face ‘complex regulatory challenges’ additional support and coordinated approvals, especially where the project spans multiple jurisdictions.
Project Ares is currently the only data centre which has been granted Major Project Status. However, it is likely that other projects in the emerging industry will meet the eligibility requirements:
- commercially viable projects with sufficient funding
- strategic significance to Australia
- an estimated investment of over $50 million, and
- unclear or complex regulatory pathways.
We expect that the NT and Federal Governments will attempt to streamline the approvals process so as to balance community concerns and economic potential of the AI boom.